johalareewi I hear you, and it's a valid point but the weather this whole year has been well down on the previous two since we got our GE system installed in terms of PV generation.
I only switched onto Agile at the beginning of August this year, 'cos we'd had a new additional battery fitted, so I felt it would be worthwhile with all the extra storage capacity.
2 weeks later, I realise that our installer has reverse connected one of our PV arrays, so we were only getting 50% generation up until that got fixed.
THEN we twig on that our capacity for storage/generation isn't what it should be - OG battery has stopped responding at all - this took over a month to get sorted. Not saying it was the fault of the outfit who installed the second battery, but it's a pretty huge coincidence.
So, I've not had the best/most lucrative initiation to Agile, but I'm in this for the long game so will be watching how it progresses closely.