Yesterday, WW messed up due to a bad update. It failed to start exporting at 4pm.

Today it's errored again - it failed to stop exporting at 7pm as set in the schedule. The WW schedule says export from 4pm-7pm. However, according to the inverter logs, the instruction WW sent to the inverter was export from 4pm-midday!

Looking at the WW Activity Log, I see: Error setting discharge-rate schedule: There were validation errors [YIHLrRqh]
Umm, I don't want the discharge-rate touched thanks. Just send the correct end time!

It seems that you have some horrible issues with WW programming that need addressing before I can trust it again.

My WattID is palatable-district


    This is what WW sent to my inverter.


    This is the WW setting. 4pm-7pm! Not 4pm-midday!

    miffy We read the current discharge rate out at the start in order to make sure we use that for the adjusted calculation.

    This weirdly was returned from Giv as -1 for your inverter and a few others, and should have been ignored, but was then passed into the adjustment calculation.

    Another knock-on effect is that the end export was not sent because of the error, indicating an unsuccessful export.

    We will deploy a fix in the next half hour. Cheers!