Imaginary-risk
1). PROBLEM
Despite repeated attempts and cancelling I could not get Quick charge to work c. . My attempts started at 0323 and looked ok in the activity log but nothing happened despite stopping and retrying at 0344. I resorted successfully in establishing a separate schedule.
2). OBSERVATION
An observation only when running my schedules.
When I specify an Export/Discharge schedule this is usefully shown on the Agile Octopus Slot calendar by means of red arrows.
The same does not occur if a Charge schedule has been specified.
The activity log, however, recognises both.
Thanks
Allen